Gladesville Bridge

Gladesville Bridge is an arch bridge in Gladesville that spans the Parramatta River, west of central Sydney, Australia. It is a few kilometres upstream of the more famous Sydney Harbour Bridge and is part of Victoria Road. At the time of its completion in 1964, Gladesville Bridge was the longest single span concrete arch ever constructed. Gladesville Bridge is the largest of a complex of three bridges, including Fig Tree Bridge and Tarban Creek Bridge, designed to carry traffic as part of the North Western Expressway.


Photo 1, Gladesville Bridge, Sydney


The bridge was the first phase of this freeway project that was to connect traffic from the Newcastle via Wahroonga/Lane Cove, then through Glebe/Annandale to connect into the city. Due to community action the freeway project was abandoned by the Wran government in 1977, leaving the Gladesville bridge connecting the existing arterial roads. 


Photo 2, Gladesville Bridge, Sydney


Gladesville Bridge


History


The current bridge replaced the original Gladesville Bridge, which was completed in 1881. The old Gladesville Bridge was constructed as part of a spate of bridge building that took place during the 1880s, which also saw the construction of the Fig Tree Bridge, Iron Cove Bridge, Glebe Island Bridge and Pyrmont Bridge. Before these bridges were built, people and goods had to cross the Parramatta River on punts or ferry services, a situation that local residents had been complaining about since the 1860s. The closest crossing was a rope-hauled ferry service between Abbotsford and Gladesville. The 1881 Gladesville Bridge was about 300 metres (980 ft) to the west of the modern bridge. This original bridge only carried one lane of traffic in each direction as well as a tramway. It featured a swing section on the southern end of the bridge that could be opened to permit sailing ships and steamers with high funnels to pass. Colliers from Newcastle would require the bridge to be opened to gain access to the Australian Gas Light Company (AGL) gasworks site at Mortlake, (now redeveloped as Breakfast Point). The bridge stood on iron cylinders with a sandstone pier at each end of the bridge. The sandstone piers are all that remain today of the original bridge. The 1964 bridge was planned and commenced as traffic demands were rising steadily in the 1950s. In addition to the old bridge often becoming a one-way crossing during peak periods, and it being used by trams, there were also several occasions during the 1960s when it could no longer be re-closed, having expanded when open due to extreme heat conditions. Construction on the new bridge started in December 1959, and took six years to complete. It was officially opened by Princess Marina on 2 October 1964. The bridge was originally opened with six traffic lanes, but the extra-wide outer lanes enabled a later reconfiguration to take place. The bridge now has three northbound lanes and four southbound lanes, separated by a concrete median.


Photo 3, Gladesville Bridge, Sydney


Design and Construction


At the time when the bridge was planned, it was anticipated that extremely large vessels would need to pass underneath it in the years to come. This, as well as the topography of the site, explains why the bridge was designed with such a high clearance. The design of the bridge was both daring and untried, yet in many ways echoed the Roman method of building arches using segmented units built over a temporary formwork. In Gladesville's case, these were hollow precast concrete blocks which were hoisted up from barges on the river, then moved down a railway on the top of the formwork into position. Every few blocks, special inflatable rubber gaskets were inserted. When all of the blocks in the arch (there are four parallel arches altogether, not seen in the picture) were in place, the gaskets were 'inflated' using synthetic hydraulic fluid, expanding the entire arch and lifting it away from the formwork to support its own weight. Once adjusted to the correct position, the gaskets were filled with liquid concrete, driving out the oil and setting to form a permanent solid arch.


Photo 4, Gladesville Bridge, Sydney


The formwork was then moved sideways and the next arch constructed in the same fashion. Once all four arches were erected, the deck was laid on top built from further precast concrete units. The arches bed into solid sandstone bedrock on either side of the river. The bridge as originally tendered for this location was a rather conventional steel cantilever bridge, but one of the contractors tendered the alternative catenary arch design, recognising it was pushing the envelope of existing bridge-building knowledge. The contractor's designer was G Maunsell & Partners of London. Their alternative was accepted after submission to the famous bridge engineer Eugène Freyssinet, who approved the design with recommendations. The inflatable gasket method for example had been pioneered by Freyssinet on much earlier designs.



Огигинал статьи «Gladesville Bridge»  -
Главная страница сайта «Мосты»  -